2017-2018 Hickory Grove/Cadillac Lane

 Contractor: Tucson Inc.

Contract Price: $383,317.28

Project Length: 1499 LF

Project Description:

  • S99001 & S00004 Cadillac Ln.: Type C Rock Riprap Toe place below Soil Encapsulated Lifts vegetated with live stakes, project transitions into Type D Rock Riprap as the bank height diminishes. Located along the north shoreline of Cadillac Ln. in the East Shore Cottage Area.
  • S99009 Hickory Grove: Three locations of Type C Rock Riprap, one of which the toe was grouted into place. The project was constructed along the southern side of the shoreline in the Hickory Grove Cottage Area.
  • S99010 Saint Andrews Ln.: Type D Rock Riprap placed along the northern most end of Saint Andrews Ln.

Click here for project location: S99001, S00004, S99009, S99010

2014-2015 Shoreline

Contractor: Mark Haynes Construction

Contract Price: $233,414.44

Project Length: 588 LF

Project Description:

  • S99083 Owls Nest: This project along the small peninsula near the Owl’s Nest (Lashley Addition) included a Cellular Confinement System (CCS) with Type B rock riprap toe and a native slope stabilization seed mix, as well as a native Riparian Buffer Custom Seed mix above the CCS. 

Click here for project location: S99083

2013-2014 Shoreline

Contractor: Tucson Inc.

Contract Price: $269,462.24

Project Length: 1445 LF

Project Description:

  • S99052 SR313: Type D rock riprap vegetated with live stake plantings, as well as two areas of 12” diameter coir log vegetated with plant plugs and a native shoreline edge custom seed mix.
  • S99051/99050/13001/99049 SR313: Type B rock riprap in 4 locations along SR 313 between TR57 (Wilson Rd) and the Sue-Lin Acres development, with several areas of a native slope stabilization custom seed mix and riparian buffer custom seed mix used to better stabilize the steep slopes above the riprap.

Click here for project location: S99052, S99051

2011-2012 Shoreline

Contractor: Stanley Miller Construction

Contract Price: $129,123.00

Project Length: 180 LF

Project Description:

  • S99004 Margo Lane: This project near the end of Margo Lane included a Cellular Confinement System (CCS) with Type C rock riprap toe, as well as a native Slope Stabilization Custom Seed mix above the CCS.
  • S11001 Margo Lane: This project near Lot S-23 on Margo Lane included a Cellular Confinement System (CCS) with Type C rock riprap toe, as well as a native Slope Stabilization Custom Seed mix above the CCS.
  • S11002 Margo Lane: This Type C rock riprap project near Lot S-19 and S-20 on Margo Lane also included live stake plantings in the riprap. 

Click here for project location: S99004, S11001, S11002

2010-2011 Shoreline

Contractor: Stanley Miller Construction

Contract Price: $352,428.21

Project Length: 1730 LF

Project Description:

  • S99033/03001 Jim Ball Rd: Type C rock riprap in three areas along Jim Ball Road.
  • S98005 Lakeview Boat Club: Type B rock riprap just south of the dam near the Lakeview Boat Club dock area
  • S99003 Margo Lane: This project near Lots S-20 and S-21 on Margo Lane was the District’s first use of the Cellular Confinement System (CCS) for bank stabilization.  The project included a Type C rock riprap toe, as well as live stake plantings installed above the CCS system.

Click here for project location: S99033, S98005, S99003

2010-2011 Shoreline

Contractor: MWCD

Project Length: 330 LF

Project Description:

  • Park Picnic Point: Type C rock riprap project located just east of Seneca Park beach.